Solid Waste Services
  • Home
  • About Project
  • Schedule
  • Progress
  • Public Involvement
  • Comments
  • Contact Us
  • More
    • Home
    • About Project
    • Schedule
    • Progress
    • Public Involvement
    • Comments
    • Contact Us
Solid Waste Services
  • Home
  • About Project
  • Schedule
  • Progress
  • Public Involvement
  • Comments
  • Contact Us

Construction by Phase

Construction Phase 1 ("Work Package 1") - Early Civil Site Work

This initial phase of work is primarily early civil site work; building out the early civil site design will be spread out over the first two phases of work. The Anchorage Assembly approved Work Package 1 in June 2020. The work began in July 2020 and includes:

  • Site clearing (e.g. removing trees and ground cover as needed) 
  • Initial site grading
  • Preparing the ground for foundations 
  • Installing some site utilities (e.g. water, sewer)

Construction Phase 2 ("Work Package 2") - Remaining Early Civil Site Work & Foundations

The second phase of work was approved by the Anchorage Assembly in August 2020. This "Work Package 2" funds the completion of the early earthwork started in Work Package 1 and allows construction to begin on the foundations and tunnel for the transfer station (aka tipping) building, the largest facility to be constructed on the campus at 87,000 square feet. Phase 2 also includes purchase and fabrication of the tipping building steel framing. The material quantities installed during this phase include:

  • 7,000 cubic yards of reinforced concrete
  • 1,200 linear feet of branch and duct bank conduit routing
  • 7,000 linear feet of utilities
  • 600 linear feet of sewer piping.

Construction Phase 3 ("Work Package 3") - All Remaining Construction

Work Package 3 will be the balance of work to fully construct the new Central Transfer Station.

Construction Phase 1 ("Work Package 1")

The three PDFs shown below are aspects of the first phase of construction. 

Page 1 is the overall site grading.

Page 2 is the water line layout.

Page 3 is the sewer line layout.

Download PDF

Construction Phase 2 ("Work Package 2")

The four PDFs shown below are aspects of the second phase of construction. 

Page 1 is a rendering of the tipping building steel framing and concrete foundations.

Page 2 is a plan drawing of the transfer station building foundations.

Page 3 is a section drawing through the tunnel of the transfer station.

Page 4 is an isometric view of the foundations, tunnel, ramps and steel framing of the transfer station building

Download PDF

Project Design

100% Design Drawings (February 2021)

Download PDF

March 2020 Project Virtual Flyover

Other Documents

If you're looking for something specific and can't find it, please shoot us an email. 


info@newswscentraltransferstation.com

April 2020 PowerPoint Update for FCC (pdf)Download
August 21, 2019 Community Meeting Summary (pdf)Download
Public Involvement Plan (pdf)Download

Copyright © 2020 Solid Waste Services - All Rights Reserved. Site last updated August 6, 2020.

Powered by GoDaddy